Test your Skills as a Product Owner

#1. What is the reason that the Daily Scrum is held in the same place and same time everyday? ? Read about
The Daily Scrum is held at the same time and place each day to reduce complexity – Scrum Guide
#2. When the Product Backlog is not ready for Sprint Planning what happens? ? Focus on the Agile Manifesto Values
Backlog refinement is not an official Scrum ceremony yet (10/18/2019). Scrum is one of the most popular Agile framework, but is is constantly being updated with valuable input from real life Scrum Masters like You!
Note: You can suggest your idea or change to the Scrum Guide here. If the idea gets popular among the Scrum.org community it may be part of the Scrum guide!
Since there is always nothing before something, if there is no concrete backlog, it is still better to re-purpose your first sprint Planning meeting (the first half which is supposed to focus on the “What” part of the Sprint Backlog) instead of letting go of the golden opportunity of all required stakeholders available for discussion of the Product Backlog refinement!
Since this event is time boxed it will be obvious how much work can be consumed into the Sprint at this early state based on the number of items we were able to discover or refine. So if you do not have a backlog to groom you can still work during Sprint Planning to refine the backlog to the extent possible. You will of course keep building more detail and add more PBIs to the top of the Backlog during the ongoing Backlog refinement sessions
Focus on the Agile Manifesto Value of “Responding to change over following a plan“
#3. An optimal Development Team has at least 5 members ? Read about the Development Team role from Scrum guide
There is no specification in Scrum that an optimal Development Team is made up of at least 5 members. Originally the ideal scrum team size was prescribed to be 7± 2. Now it is 6 ± 3. So the max is still 9, but the range was increased in the Scrum Guide as there are plenty of successful Scrum development teams with 3 or 4 members.

#4. The Development Team should have all the skills needed to: ? Read about
They are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality – Scrum Guide
#5. The Development Team should have all the skills needed to: ? Read about the Scrum Development Team from the Scrum Guide
The Development Team consists of professionals who do the work of delivering a potentially releasable Increment of “Done” product at the end of each Sprint. – Scrum Guide
#6. What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity? ? Read about the Scrum Master role and his services to the development team from the Scrum guide on Scrum.org
The Scrum Master service to the development team includes :
- Removing impediments to the Development Team’s progress;
- Facilitating Scrum events as requested or needed; and,
#7. A very senior manager of the firm asks the Development Team to add a “very important” item to the current Sprint. What should the Development Team do?
When Scrum is matured at an organization the senior manager would know not to contact the team directly interfering with their current sprint goal and backlog. The sprint backlog items have been selected as most valuable by the Product Owner. No changes should be made that endanger the Sprint Goal. No changes can be pushed on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog). The PO however can work with the development team to add/drop work to sprint backlog anytime during the sprint.
#8. What are the benefits of self-organization?
Increased Commitment, Accountability and Creativity are the direct results of a self-organizing team
#9. What is the primary role of Management in Scrum? ? Think about how the Management can
Management has to support the Scrum Teams with insights and resources that help them improve.
#10. When is the work planned for the first days of a Sprint decomposed?
Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less. – Scrum Guide